Government Contracting

Construction Project Delivery Methods Comparison 2025: DBB vs DB vs CM

Compare construction project delivery methods. Learn the differences between Design-Bid-Build, Design-Build, CM/GC, and other delivery approaches for government contracts.

BidFinds Government Contracting Team
December 24, 2025
15 min read

Quick Answer: Which Delivery Method is Best?

It depends on your project priorities. Design-Bid-Build offers low price through competition but takes longest. Design-Build is fastest with single-point accountability. CM/GC provides early contractor involvement and flexible pricing. Each has tradeoffs between cost, schedule, risk, and owner control.

DBB
Lowest Price
DB
Fastest Schedule
CM/GC
Most Collaborative
IPD
Best Integration

Design-Bid-Build (DBB)

The traditional method with sequential design, bidding, and construction:

How DBB Works

Phase 1: Design

Owner hires designer to complete 100% construction documents.

Phase 2: Bid

Competitive bidding among contractors on completed design.

Phase 3: Build

Selected contractor builds per the documents.

Advantages

  • ✓ Competitive pricing
  • ✓ Clear scope before bidding
  • ✓ Owner controls design
  • ✓ Well-understood process
  • ✓ Easy to compare bids

Disadvantages

  • ✗ Longest overall schedule
  • ✗ No contractor input in design
  • ✗ Change order risk from design issues
  • ✗ Adversarial relationships possible
  • ✗ Lowest price may not be best value

Design-Build (DB)

Single entity responsible for both design and construction:

How DB Works

Phase 1: RFP

Owner defines requirements and performance criteria.

Phase 2: Selection

Best value selection of design-builder team.

Phase 3: Execute

Design-builder completes design and construction.

Advantages

  • ✓ Fastest delivery schedule
  • ✓ Single point of accountability
  • ✓ Early cost certainty possible
  • ✓ Design/construction integration
  • ✓ Reduced owner administration

Disadvantages

  • ✗ Less owner control of design
  • ✗ Price comparison difficult
  • ✗ Requires detailed criteria documents
  • ✗ Design quality concerns
  • ✗ Higher proposal costs

CM/GC and CMAR

Construction Manager/General Contractor brings contractor expertise during design:

How CM/GC Works

Phase 1: Selection

Select CM/GC based on qualifications early in design.

Phase 2: Preconstruction

CM provides estimating, scheduling, and constructability input.

Phase 3: Construction

Convert to GMP or lump sum for construction phase.

Advantages

  • ✓ Contractor input improves design
  • ✓ Better cost certainty through process
  • ✓ Collaborative relationships
  • ✓ Owner retains design control
  • ✓ Flexible GMP timing

Disadvantages

  • ✗ Less price competition
  • ✗ GMP negotiation required
  • ✗ More complex contracts
  • ✗ Higher preconstruction costs
  • ✗ Open book pricing concerns

Other Delivery Methods

Integrated Project Delivery (IPD)

Multi-party agreement with shared risk/reward among owner, designer, and contractor from project inception.

  • • Highest collaboration
  • • Aligned incentives
  • • Complex contracting
  • • Requires mature partners

Job Order Contracting (JOC)

Indefinite delivery/indefinite quantity contract for repetitive work using pre-priced unit price book.

  • • Fast task order execution
  • • Pre-negotiated pricing
  • • Best for smaller projects
  • • Less suited for complex work

Multi-Prime

Owner contracts directly with multiple trade contractors, managing coordination themselves or through CM.

  • • Direct trade relationships
  • • Eliminates GC markup
  • • Higher owner risk
  • • Complex coordination

Progressive Design-Build

Hybrid combining early design-builder selection with progressive pricing through design development.

  • • Earlier collaboration
  • • More owner input than DB
  • • Progressive cost refinement
  • • Flexible off-ramp options

Side-by-Side Comparison

FactorDBBDBCM/GC
ScheduleLongestFastestMiddle
Price CompetitionHighestLimitedNegotiated
Design ControlFullLimitedFull
Change Order RiskHigherLowerLower
CollaborationLowerModerateHighest
Owner Expertise RequiredModerateHighHigh

Choosing the Right Method

Match the delivery method to project needs:

Selection Guidance

Choose DBB When:

Clear, well-defined scope; lowest price is priority; schedule is flexible; owner has strong design team; standard construction; budget certainty needed before construction starts.

Choose DB When:

Fast schedule is critical; single point of accountability desired; performance criteria are clear; owner comfortable with less design control; innovative solutions welcome.

Choose CM/GC When:

Complex project benefits from contractor input; owner wants design control; budget needs refinement through design; collaboration valued; phased construction may be needed.

Frequently Asked Questions

Which method is cheapest?

DBB typically yields lowest bid price due to competitive bidding. However, total project cost including change orders may favor DB or CM/GC for complex projects.

Can federal agencies use all these methods?

Yes. Federal agencies have authority to use DBB, DB, and CM at-Risk delivery methods. Selection should be based on project needs and documented rationale.

How do I bid on different delivery methods?

DBB: Compete on price with completed design. DB: Propose design concept and price, often best value. CM/GC: Compete on qualifications and fee, then negotiate GMP.

Which method has the most opportunities?

DBB remains most common, especially for public projects. DB is growing rapidly. CM/GC usage varies by region and owner. Diversify your capabilities to pursue all methods.

Find Projects Matching Your Expertise

BidFinds helps you discover construction opportunities across all delivery methods. Filter by delivery type to find the right fit.

Start Finding Bids

Ready to Find Your Next Contract?

Get instant access to thousands of government construction bids with our AI-powered platform.

Get Started