Contract Management

Government Contract Modifications Guide 2025: Types & Process

Complete guide to government contract modifications. Learn about bilateral and unilateral modifications, change orders, equitable adjustments, and how to protect your rights.

BidFinds Government Contracting Team
December 26, 2025
10 min read

Quick Answer: Contract Modifications

Contract modifications are written changes to the terms of an existing government contract. They can be bilateral(both parties agree) or unilateral (government directs). Modifications can change scope, price, schedule, or other contract terms.

Bilateral
Mutual Agreement
Unilateral
Government Directed
SF-30
Standard Form

Types of Contract Modifications

Bilateral Modifications

Both parties must agree:

  • Supplemental agreements
  • Negotiated changes
  • Definitization of change orders
  • Option exercises

Unilateral Modifications

Government can issue without agreement:

  • Administrative changes
  • Changes under Changes clause
  • Termination notices
  • Exercise of options

The Changes Clause

The Changes clause (FAR 52.243) gives the government the right to make unilateral changes to the contract within the general scope. The contractor must comply but is entitled to an equitable adjustment.

Types of Changes

Drawings/Specifications

Technical requirement changes

Method of Shipment

Delivery method changes

Place of Delivery

Location changes

Packaging/Packing

Shipping requirement changes

Important: Scope Limitation

Changes must be within the general scope of the contract. Changes outside the scope require a new contract or sole-source justification—they cannot be made unilaterally.

Request for Equitable Adjustment (REA)

When a change increases or decreases costs or time, the contractor is entitled to an equitable adjustment. Submit an REA to recover additional costs.

REA Components

Direct Costs

Labor, materials, and other direct costs attributable to the change

Indirect Costs

Overhead and G&A applicable to the change

Profit

Reasonable profit on the changed work

Schedule Impact

Time extension if change delays delivery

REA Submission Tips

  • Submit promptly after change
  • Document everything
  • Segregate change costs from base costs
  • Include supporting calculations

Modification Process

Steps to Execute a Modification

1

Identify the Change

Recognize when a change has occurred or is needed

2

Notify the CO

Provide written notice of the change and its impact

3

Submit Proposal

Provide detailed cost and schedule impact

4

Negotiate

Work with CO to agree on equitable adjustment

5

Execute Modification

Sign SF-30 to formalize the change

Frequently Asked Questions

What if I disagree with a unilateral change?

You must continue performing as directed. However, reserve your rights in writing and submit an REA or claim for the equitable adjustment you believe you're entitled to.

Is there a time limit for submitting REAs?

Submit REAs as soon as practicable. While there's no strict deadline for REAs (unlike claims), delayed submission weakens your position and may raise waiver issues.

What's the difference between an REA and a claim?

An REA is a request for negotiation. A claim is a formal demand under the Contract Disputes Act requiring a contracting officer's final decision, which can be appealed.

Find Government Contract Opportunities

Build your contract portfolio with BidFinds.

Get Started →

Related Articles

Ready to Find Your Next Contract?

Get instant access to thousands of government construction bids with our AI-powered platform.

Get Started