Contract Administration

Government Contract Modifications Guide: Change Orders, REAs & Equitable Adjustments

Master government contract modifications including change orders, requests for equitable adjustment (REAs), and constructive changes. Learn how to protect your rights and maximize recovery on federal construction contracts.

BidFinds Government Contracting Team
December 22, 2025
18 min read

Introduction to Contract Modifications

Contract modifications are an inevitable part of government construction projects. Whether due to changed conditions, design errors, or new requirements, understanding how to navigate the modification process is critical to protecting your business and ensuring fair compensation.

Contract Modification Statistics

65%

Federal construction contracts receive modifications

12-15%

Average value increase through modifications

$50B+

Annual contract modification value government-wide

45%

Of disputes stem from modification disagreements

The Federal Acquisition Regulation (FAR) provides the framework for contract modifications, but successfully navigating this process requires understanding both your rights and obligations. This guide will help you protect your interests while maintaining productive government relationships.

Types of Contract Modifications

Bilateral Modifications

Bilateral modifications (also called supplemental agreements) require agreement from both the contractor and the government. They are used for:

  • Negotiated equitable adjustments - Pricing changes for directed work
  • Definitization of letter contracts - Finalizing preliminary agreements
  • Reflecting other agreements - Settlement of claims or disputes
  • Option exercises - When options require negotiation

Unilateral Modifications

Unilateral modifications are signed only by the contracting officer. They are authorized for:

  • Administrative changes - Corrections, name changes, address updates
  • Changes under the Changes clause - Directed scope changes
  • Option exercises - When terms are predetermined
  • Property changes - Government property adjustments

Key Distinction

When the government issues a unilateral change order, you must comply and perform the work even if you disagree with the pricing. Your remedy is to submit a Request for Equitable Adjustment (REA) or, if not resolved, a formal claim under the Contract Disputes Act. Never stop work over a pricing disagreement unless the change is outside the general scope of the contract.

Understanding the Changes Clause

The Changes clause (FAR 52.243-4 for construction) is one of the most important provisions in government contracts. It gives the contracting officer authority to make changes within the general scope of the contract and establishes your right to equitable adjustment.

What the CO Can Change

Specifications (including drawings and designs)
Method or manner of performance
Government-furnished property or services
Directing acceleration of performance
Place of performance
Amount of government-furnished property

Your Rights Under the Changes Clause

  • Equitable adjustment in price - Increased costs (direct, indirect, and profit)
  • Time extension - Additional time for performance
  • Price decrease - Deductive changes reduce contract price
  • Assertion deadline - 30 days to submit written notice (but continue performing)

Critical: Scope Limitations

Changes must be within the "general scope" of the contract. Cardinal changes—those that fundamentally alter the nature of the contract—are outside the Changes clause and may constitute a breach. Examples include changing a building renovation into new construction or significantly increasing the contract value (typically 50%+ increase raises concerns).

Constructive Changes Doctrine

Constructive changes occur when the government, without issuing a formal change order, effectively requires the contractor to perform work beyond the contract requirements. Recognizing and documenting constructive changes is essential for cost recovery.

Common Types of Constructive Changes

Defective Specifications

Government-provided drawings, designs, or specifications that are impossible to follow, internally inconsistent, or contain errors requiring additional work to correct.

Acceleration

Requiring the contractor to maintain the original schedule despite excusable delays, or demanding completion earlier than contractually required.

Superior Knowledge

Government withholds vital information that would have affected the contractor's bid or performance approach, causing increased costs.

Overinspection

Requiring work quality or standards beyond contract requirements through inspection rejection or additional testing requirements.

Interference/Disruption

Government actions that hinder contractor performance, such as late site access, delayed approvals, or coordination failures.

Oral Directions

Verbal instructions from government personnel that result in additional work or changes to the manner of performance.

Elements to Prove a Constructive Change

  1. 1The contractor performed work beyond the contract requirements
  2. 2The extra work was ordered or caused by the government (expressly or impliedly)
  3. 3The contractor incurred additional costs as a result
  4. 4The contractor provided timely notice (even if informal)

Request for Equitable Adjustment (REA) Process

A Request for Equitable Adjustment (REA) is your formal request for compensation due to changes, differing site conditions, or other government actions. Unlike a claim, an REA is a negotiating tool that doesn't trigger the formal disputes process.

REA vs. Claim: Key Differences

AspectREAClaim
NatureNegotiating toolFormal legal demand
CertificationNot requiredRequired if over $100K
CO ResponseNo deadline60 days (written decision)
InterestNot applicableAccrues from submission
Appeal RightsMust convert to claimBoard/Court of Federal Claims
RelationshipCollaborativeAdversarial

REA Components

1. Executive Summary

Brief overview of the change, impact, and requested adjustment

2. Factual Background

Chronological narrative of events leading to the change

3. Entitlement Analysis

Legal and contractual basis for the adjustment (cite clauses)

4. Quantum/Cost Analysis

Detailed breakdown of direct costs, indirect costs, and profit

5. Schedule Impact

Time extension request with critical path analysis

6. Supporting Documentation

Daily logs, correspondence, photos, invoices, schedules

Pricing Contract Modifications

Proper pricing of modifications requires understanding allowable costs and calculation methods recognized by the government. The goal is to demonstrate the actual cost impact of the change.

Cost Elements in Equitable Adjustments

Direct Costs

  • • Labor (with burden rates)
  • • Materials and supplies
  • • Equipment (ownership or rental)
  • • Subcontractor costs
  • • Other direct costs (permits, testing, etc.)

Indirect Costs (Overhead)

  • • Field overhead (job site supervision, temporary facilities)
  • • Home office overhead (G&A expenses)
  • • Extended overhead for delay claims

Profit

  • • Typically 10-15% on direct costs
  • • May be reduced for subcontractor pass-through
  • • Weighted guidelines method for large modifications

Pricing Methods

Actual Cost Method

Preferred when:

  • • Work is complete
  • • Good cost records exist
  • • Costs are segregated

Estimated Cost Method

Used when:

  • • Work is prospective
  • • Detailed estimates needed
  • • Unit prices available

Total Cost Method

Last resort when:

  • • Costs cannot be segregated
  • • Must prove other methods impractical
  • • Original bid was reasonable

Jury Verdict Method

Tribunal approach:

  • • When exact damages uncertain
  • • Reasonable approximation
  • • Based on available evidence

Documentation Requirements

The strength of any modification request depends on documentation. Start documenting from day one— you never know which issues will become significant claims.

Essential Documentation

Daily Records

  • Daily logs with manpower counts
  • Equipment utilization records
  • Weather conditions
  • Work performed by area
  • Delays and disruptions noted

Correspondence

  • RFIs and responses
  • Meeting minutes
  • Emails and letters
  • Submittals and approvals
  • Notice letters

Cost Records

  • Payroll records and timesheets
  • Material invoices and receipts
  • Equipment rental agreements
  • Subcontractor invoices
  • Job cost reports

Visual Evidence

  • Dated photographs
  • Video documentation
  • As-built drawings
  • Schedule updates
  • Progress reports

Pro Tip: Force Account Records

When performing change order work, request that the government representative sign daily "force account" records acknowledging the labor, equipment, and materials used. These contemporaneous records signed by the government are powerful evidence for pricing negotiations.

Contract Disputes Process

When REA negotiations fail, the Contract Disputes Act (CDA) provides your path to resolution. Understanding this process is essential for protecting your rights.

CDA Timeline

1

Submit Certified Claim

For claims over $100K, certification required. 6-year statute of limitations.

2

CO Final Decision

60 days for claims under $100K; reasonable time for larger claims.

3

Appeal (if denied)

90 days to Board of Contract Appeals OR 12 months to Court of Federal Claims.

4

ADR Options

Boards offer mediation, summary trial, and other ADR procedures.

Claim Certification Requirements

For claims exceeding $100,000, the contractor must certify:

"I certify that the claim is made in good faith; that the supporting data are accurate and complete to the best of my knowledge and belief; that the amount requested accurately reflects the contract adjustment for which the contractor believes the Government is liable; and that I am duly authorized to certify the claim on behalf of the contractor."

Warning: False certification can result in penalties under the False Claims Act, including treble damages and criminal liability.

Best Practices for Contractors

Protect Your Rights

  • • Provide timely written notice of changes
  • • Never waive rights in modification signatures
  • • Reserve rights when signing under protest
  • • Keep copies of all signed documents
  • • Document oral directions in writing
  • • Know your contract notice requirements

Documentation Habits

  • • Maintain detailed daily logs
  • • Photograph conditions before and after
  • • Track costs by change order work
  • • Save all correspondence chronologically
  • • Update schedules to show impacts
  • • Document government-caused delays

Pricing Success

  • • Use actual costs when available
  • • Provide detailed cost breakdowns
  • • Support overhead with auditable rates
  • • Request force account signatures
  • • Don't inflate—government audits claims
  • • Include schedule impact analysis

Relationship Management

  • • Communicate early and often
  • • Resolve issues at lowest level first
  • • Be professional, not adversarial
  • • Understand CO authority limits
  • • Use REAs before escalating to claims
  • • Consider long-term relationship value

The Golden Rule of Changes

Continue performing. Unless a change is clearly outside the contract scope (cardinal change), you must continue working while disputing the pricing. Stopping work over an REA disagreement puts you in breach and jeopardizes your position. Document everything, submit your REA, and keep building.

Find Government Construction Contracts

BidFinds helps contractors discover federal, state, and local construction opportunities. Start building your government contracting portfolio today.

Start Your Free Trial

Related Articles

Ready to Find Your Next Contract?

Get instant access to thousands of government construction bids with our AI-powered platform.

Get Started